City Road Nakano-cho Route 52 School Route Safety Measure Construction

Contracting organization: Mihara City, Hiroshima

1. Items Subject to Bidding City Road Nakano-cho Route 52 School Route Safety Measure Construction 2. Construction Location 9-chome, Nakano-cho, Mihara City 3. Construction Type Civil engineering works (Doboku-isshiki) 4. Construction Overview Construction length: L=301.6m Road earthworks: 1 set Retaining wall work: V=147m3 Drainage structure work: L=491m Catchment pit work: N=13 locations Protective fence work: L=30m Paving work: A=1728m2 Lane marking work: L=359m 5. Construction Period From the day following the contract date to March 31, 2027 6. Schedule and Deadlines Bid participation app…