Hiwano Forest Road Improvement Construction
Contracting organization: Hokusatsu District Forest Office, Kyushu Regional Forest Office, Forestry Agency
1. Items Subject to Bidding(1) Project Name: Hiwano Forest Road Improvement Construction(2) Location: Hiwano, Satsuma-cho, Satsuma-gun, Kagoshima Prefecture(3) Scope of Work:Total length: 78.0m, Total width: 3.6mImprovement Section 1: Length 50.0m, Concrete pavement 159.5m2, Concrete retaining wall 163.0m3, etc.Improvement Section 2: Length 28.0m, Concrete pavement 87.0m2, Concrete retaining wall 91.1m3, etc.(4) Contract Period: From the day following the contract date to March 12, 2027. Construction must commence by September 18, 2026.(5) Procurement Method: This project uses a construction …